proba3
Prior to the awarding and deployment of the network, the DPC CN is configured and implemented, located in the basement of the Omega building.
The network award takes place (see milestone 5), and the contracting process is carried out.
Once the contract is formalized, the network deployment and coordination of associated activities begins.
Award of the instrumentation equipment.
In preparation for the network deployment, mobile network terminals (MNT) compatible with FR1 and FR2 frequency bands have been acquired. In this phase, six mobile devices for the FR1 band and one mobile device for the FR2 band were incorporated. The acquisition of the remaining three terminals for FR2 is scheduled for the last quarter of 2025 and throughout 2026.