Proba4

The requested instrumentation is delivered: signal analyzer and optical and RF spectrum analyzers.

Completion of network deployment and verification of overall functionality — marked in orange — due to a delay compared to the initially scheduled date, which was set for early April and is now estimated to be mid-June.

Once the infrastructure is functioning correctly, training is conducted, and the network is handed over.

The exploitation model is defined by establishing services for the research community, as well as managing the operation and maintenance of the network.

The final project documentation is completed and submitted to the Ministry for Digital Transformation and Public Service as justification for the network financing. The exploitation, operation, and maintenance phase then begins.